Feasibility Study (Client RHD):

Project Name

Service Provided

Feasibility Study and Detailed Engineering Design and Construction supervision of Sylhet – Tamabil - Jaflong Road Improvement Project.

Feasibility Study and Detailed Engineering Design and Construction supervision

Feasibility Study and Detailed Engineering Design and Construction supervision of Hazrat Shah Paran (2nd Surma ) Bridge & Other Drainage Structures under Sylhet – Tamabil - Jaflong Road Improvement Project.

Feasibility Study and Detailed Engineering Design and Construction supervision

Feasibility Study and Preliminary Design of Katchpur Grade Separated (Flyover) Junction Additional Work Rehabilitation of Dhaka-Sylhet Road under RRMP III, Funded by IDA.

Feasibility Study and Preliminary Design

Feasibility Study(Client BBA):

Project Name

Service Provided

Feasibility Study of Construction of Bridge at Ferry Location at 70thKm. on Labukhali – Dumki – Boga – Dashmina – Golachipa – AmragachiRoad (Z8806)

 

(Length 1580 m)

  1. Detailed Traffic Survey with O-D Survey, Traffic Analysis and Traffic Forecast etc.
  2. Optimization of length, location and alignment of bridge.
  3. Geotechnical investigation, geological mapping; seismic study, hydrological and morphological survey.
  4. Detailed EIA and EMMP.
  5. Assessment of resettlement requirements and preparation of action plan.
  6. Preliminary design of the bridge, approach roads, river training works with cost estimation.
  7. Land Acquisition Plan.
  8. Economic and financial evaluation determining EIRR, NPV, BCR, FIRR etc.
  9. Transfer of knowledge.

Feasibility Study of Construction of Bridge at Ferry Location at 53rdKm. on Barishal – Jhalokhati – Bhandaria – PerojpurRoad (R870)

 

(Length 1520 m)

  1. Detailed Traffic Survey with O-D Survey, Traffic Analysis and Traffic Forecast etc.
  2. Optimization of length, location and alignment of bridge.
  3. Geotechnical investigation, geological mapping; seismic study, hydrological and morphological survey.
  4. Detailed EIA and EMMP.
  5. Assessment of resettlement requirements and preparation of action plan.
  6. Preliminary design of the bridge, approach roads, river training works with cost estimation.
  7. Land Acquisition Plan.
  8. Economic and financial evaluation determining EIRR, NPV, BCR, FIRR etc.
  9. Transfer of knowledge.

Feasibility Study of Construction of Bridge at Ferry Location at 8thKm. on Rahmatpur – Babugonj – Muladia – HizlakokRoad (Z8034).

 

(Length 1580 m)

  1. Detailed Traffic Survey with O-D Survey, Traffic Analysis and Traffic Forecast etc.
  2. Optimization of length, location and alignment of bridge.
  3. Geotechnical investigation, geological mapping; seismic study, hydrological and morphological survey.
  4. Detailed EIA and EMMP.
  5. Assessment of resettlement requirements and preparation of action plan.
  6. Preliminary design of the bridge, approach roads, river training works with cost estimation.
  7. Land Acquisition Plan.
  8. Economic and financial evaluation determining EIRR, NPV, BCR, FIRR etc.
  9. Transfer of knowledge.

Feasibility Study for Construction of Bridge at Ferry Location at 17thKm on Kachua – Betagi – Patuakhali – Lohalia – KalayaRoad (Z8052)

 

(Length 1730 m)

  1. Detailed Traffic Survey with O-D Survey, Traffic Analysis and Traffic Forecast etc.
  2. Optimization of length, location and alignment of bridge.
  3. Geotechnical investigation, geological mapping; seismic study, hydrological and morphological survey.
  4. Detailed EIA and EMMP.
  5. Assessment of resettlement requirements and preparation of action plan.
  6. Preliminary design of the bridge, approach roads, river training works with cost estimation.
  7. Land Acquisition Plan.
  8. Economic and financial evaluation determining EIRR, NPV, BCR, FIRR etc.
  9. Transfer of knowledge.

Feasibility Study for Dhaka Elevated Expressway PPP project, Dhaka.

  1. Detailed Traffic Survey with O-D Survey, Traffic Analysis and Traffic Forecast etc.
  2. Geotechnical investigation.
  3. Assessment of resettlement requirements and preparation of action plan.
  4. Land Acquisition Plan.
  5. Economic and financial evaluation determining EIRR, NPV, BCR, FIRR etc.

Feasibility Study (Client GDTPCB):

Project Name

Service Provided

Dhaka Urban Transport Project (DUTP)

Feasibility Study of Jatrabari Flyover

Design review and Construction Supervision of Mohakhali Flyover.

Construction supervision of three no. interdistrict Bus Terminal.

Design review and construction supervision of 12 no. foot over Bridge.

Maitanance and beautification of Dhakacity Corporation Road.

Feasibility Study & Design review and Construction Supervision

Feasibility Study (Client LGED):

Project Name

Service Provided

Feasibility Study of 04 nos Large Bridges in Jamalpur District.

The Scope of Consultancy Services included: 

Survey: 

  1. Detail Traffic Survey
  2. Social Survey 

Analysis: 

  1. Benefit Cost Ratio (BCR)
  2. Net Present Value (NPV)
  3. Economic Internal Rate of Return (EIRR)
  4. Financial Internal Rate of Return (FIRR)
  5. Public views regarding the impact of proposal construction

Economical Analysis of Important 05 (Five) Large Bridges on Netrakona District.

The Scope of Consultancy Services included: 

Survey: 

  1. Detail Traffic Survey
  2. Social Survey 

Analysis: 

  1. Benefit Cost Ratio (BCR)
  2. Net Present Value (NPV)
  3. Economic Internal Rate of Return (EIRR)
  4. Financial Internal Rate of Return (FIRR)
  5. Public views regarding the impact of proposal construction